The City of Excelsior created “The Commons Master Plan” in 2017 to address the infrastructure needs of The Commons. This ambitious plan was the result of a multi-year, community-driven process that sought to establish a shared vision for the future of this historic and iconic park.

The Commons Master Plan includes many improvements while maintaining the historic features that are still very popular with park-goers. Community for The Commons is dedicated to helping turn this vision into a reality, hosting events and raising necessary funds with public and private support.

Thanks to the City of Excelsior staff and council members, plus tremendous support from the community and many generous donors, several renovations have already been successfully completed.

Completed Master Plan Projects


The Pavilion

Chosen as the first Master Plan project because of its prominence, symbolic importance and community interest. Its thoughtful design opens up spacious views of the Park and Lake Minnetonka with a multi-purpose bandshell and stage for concerts, gatherings and events. People can enjoy concerts from the lake or The Commons with the open-air design.

The pavilion before and after the rebuild.

  • 2020- PAC formed

  • 2021 – approved by the City Council, completed

  • VJAA Architects designed the wave-like open air pavilion in collaboration with landscape architecture firm Damon Farber who designed the surrounding native gardens and hillside seating and Gardner Builders did the construction management and general contracting

The Plaza

A wonderful complement to the Pavilion in its’ design and flow acts as a community hub and gathering space featuring covered seating, outdoor seating areas with integrated fire-pits and family restrooms.

The plaza before and after the rebuild.

  • 2021 – PAC formed

  • 2022 – approved by the City Council, completed

  • VJAA Architects designed the structure, Damon Farber designed the surrounding landscape, green roof and stormwater management, and Gardner Builders did the construction management and general contracting

The Ballpark

This renovation included new dugouts, drain tile and sod, rain gardens, state of the art lighting and restoration of the historic WPA seating area.

The ballpark before and after the rebuild.

  • 2025 – started, approved by the City Council

  • 2026 – Completed

  • HKGI was hired to design and reconstruct the ball field area

What’s Coming Next in the Master Plan?


The Mini Master Plan

On August 17, the Excelsior City Council approved the Commons Mini Master Plan — the next chapter for our favorite gathering place. Starting in 2027, we begin the next phase: playground, beach house, pickleball and tennis courts, and beach and adventure docks — more ways to play, gather, and relax, all shaped by this community.


How was the Mini Master Plan Developed?